Stormwater Requirements Across Regional NSW: Builder’s Guide
How stormwater and OSD requirements differ across regional NSW councils - Shoalhaven, Wagga Wagga, Dubbo, Tamworth and Albury - and…
Read article
Sutherland Shire continues to redevelop steadily, with duplexes and townhouses transforming streets in Caringbah, Miranda, Kirrawee and Sutherland, apartment activity around Cronulla and the Kirrawee brick-pit precinct, and ongoing greenfield and infill growth around Menai, Barden Ridge and Engadine. The 2023 changes to dual occupancy controls in parts of Sydney have kept demand for two-dwelling sites strong across the Shire.
Every one of those projects must satisfy Council’s stormwater controls, and in this LGA they are spelled out in unusual detail.
The key document is Sutherland Shire Development Control Plan 2015, and specifically Chapter 38 – Stormwater and Groundwater Management. It works alongside Sutherland Shire Local Environmental Plan 2015 and Council’s Environmental Specification – Stormwater Management, which governs the detailed design and construction of drainage and water quality devices.
Chapter 38 covers drainage design, on-site detention, water quality, groundwater and overland flow, and includes principles that catch builders out – for example, stormwater cannot be diverted from one drainage sub-catchment to another, and site levels cannot be changed to redirect runoff to a different sub-catchment.
Permissible site discharge rates and storage volumes are calculated under Chapter 38’s clauses and should be confirmed current with Council or your engineer at design time.
The Shire is framed by water: the Georges River to the north and west, the Woronora River through the middle, and Port Hacking to the south, with the Royal National Park beyond. These receiving waters are central to the Shire’s identity, which is why Council pairs detention with genuine water quality requirements.
Topography matters too. Sandstone plateaus fall steeply to the rivers, so many sites combine shallow rock (driving up OSD excavation costs) with steep rear yards draining to bushland. Around Cronulla and low-lying foreshore areas, flat grades and tidal influence can complicate gravity discharge, while dune sands change infiltration behaviour. Menai and Barden Ridge sites often deal with bushland interfaces where uncontrolled discharge causes erosion.
Contrive Consultants prepares Chapter 38-compliant stormwater and OSD designs for duplexes, townhouses and commercial projects across the Sutherland Shire, from Cronulla to Menai. Review our engineering services or reach out – call +61 497 848 111 or email info@contriveconsultants.com.au.
How stormwater and OSD requirements differ across regional NSW councils - Shoalhaven, Wagga Wagga, Dubbo, Tamworth and Albury - and…
Read articleLiverpool DCP 2008 stormwater and OSD rules - what builders in Austral, Leppington and Edmondson Park must include in their…
Read articlePenrith DCP 2014 stormwater rules explained - OSD, WSUD and drainage plan requirements for builders in Jordan Springs, Glenmore Park…
Read article