Ask most NSW builders about telecommunications on a duplex or townhouse project and you will get a shrug: “the sparky runs a conduit, doesn’t he?” Sometimes that is true. More often, it is how projects end up with an occupation certificate delayed because there is no compliant lead-in, no NBN application on record, and no way to get four townhouses connected without cutting a brand-new driveway.
Multi-dwelling developments – dual occupancies, duplexes, villas, terraces and townhouses – sit in an awkward middle ground for telecommunications. They are too small to have a project manager chasing utilities full time, but too complex for the single-dwelling assumption that “the NBN is already in the street” to hold. This article explains what telecommunications infrastructure these projects actually need, how the design scales from a duplex to a large townhouse site, and how to keep the NBN process from becoming the last, most annoying item on your completion checklist. It is written from the delivery experience of Pit and Pipe, the telecommunications design consultancy within the Rouse Hill–based Contrive group.
Under the Australian Government’s telecommunications-in-new-developments policy, developers – and on small projects that usually means the builder – are responsible for providing fibre-ready facilities for every new dwelling, unit or lot they create. A knock-down rebuild of a single house can often reuse the existing lead-in. The moment you create additional dwellings, you are creating additional connections, and each one needs its own compliant pathway from the street network to the building.
That pathway is passive infrastructure: conduits, pits where required, building entry provisions and first-point-of-entry arrangements. NBN Co brings the fibre; you provide the route it travels. For multi-dwelling projects the design question is not whether you need it, but how much of it, and in what configuration.
For a two-dwelling project fronting an existing street, the infrastructure is usually modest: a lead-in conduit from the existing street pit (or a new pit if none is suitably located) to each dwelling, or a single lead-in to a shared point with internal distribution. The design must still meet NBN Co’s specifications – correct conduit size (typically P23 for lead-ins), bend radii, cover depths and draw rope – and the project still needs an NBN New Developments application so each dwelling is recorded, serviceable and able to order a connection at completion.
The most common duplex mistake is forgetting the second lead-in entirely, because the site “already has NBN”. It has one connection. Your project needs two.
Once dwellings sit behind others on a common access way, the infrastructure starts to look like a miniature subdivision: a lead-in from the street network, then a reticulated run of conduits (and pits where run lengths, bends or junctions require them) along the driveway, with an individual lead-in branching to each dwelling. The design has to coordinate with everything else fighting for space in that driveway corridor – stormwater lines, sewer junctions, electrical consumer mains, gas and the driveway pavement profile itself.
This is the scale at which a designed, documented solution stops being optional. Pit placement needs to survive vehicle loads or be located out of trafficable areas; conduit depth needs to survive driveway construction; and every dwelling needs its entry point positioned to suit the internal cabling plan.
On larger multi-dwelling sites – a dozen or more dwellings, internal roads, staged construction – the telecommunications design becomes a genuine network design: distribution conduits (P50/P100), jointing and hauling pits, lead-ins to every dwelling, and a clearly designed connection point to NBN Co’s external network. These projects typically follow the full pit and pipe pathway: application, service plan or master plan, NBN design review, construction to specification, compliance certification and transfer of the network to NBN Co before fibre is hauled.
Staging matters here. If you are building in two stages, the network architecture should let stage one become ready for service without waiting for stage two’s civil works – otherwise your first settlements are waiting on trenching at the far end of the site.
Telecommunications design does not stop at the wall. Each dwelling needs a building entry provision and an internal pathway to wherever the network termination device will live. On attached forms – duplexes, terraces, manor houses – decisions about shared versus individual entries, riser locations and the position of communications enclosures are much cheaper to make on the drawings than on site. Class 2 buildings (apartments) bring additional requirements again, including communications rooms and riser design, which is a topic in its own right.
Good practice for townhouse projects is simple: show the telecommunications entry and internal conduit route on the architectural and services drawings, in the same coordination pass as electrical and hydraulic services. When the group’s architects at ARQI and the civil team at Contrive Consultants are working on the same project as Pit and Pipe, that coordination happens as a matter of course – the conduit route is on the drawings before the slab is designed, not marked up in texta after it is poured.
The process mirrors the subdivision pathway, scaled down:
The single most valuable thing a builder can do is lodge the application early. On a townhouse project, telecommunications lead time is comfortably absorbed if the application goes in around construction certificate stage. Lodged at practical completion, it becomes the item everyone is waiting on.
Telecommunications on a multi-dwelling project is not expensive relative to the works around it – the conduits share trenches that are being dug anyway, and the design cost is small against the cost of delayed occupation certificates or retrofit works. The economics only go bad when the work is unplanned: separate mobilisation to trench after the site is finished, redesign because the as-built layout cannot be certified, or settlement delays while an eleventh-hour NBN application grinds through assessment.
Treat it like any other engineered service: design it once, coordinate it with the civil and architectural documentation, install it with the main works, certify it progressively. On that footing it is one of the smoothest approvals in the whole project.
Yes, in almost all cases. You are creating an additional dwelling that needs its own serviceable connection, and NBN Co’s new-developments process is how that dwelling gets registered and connected. The existing house’s connection does not cover the new dwelling. The application is straightforward for small projects, but it needs to be lodged – ideally early in construction.
The developer entity is responsible for providing fibre-ready facilities, and on small projects the builder frequently acts as the developer’s agent (or is the developer). Practically, whoever controls the civil works needs to own the task, because the conduits must go in with the trenching. You can nominate a consultant such as Pit and Pipe to lodge and manage the NBN application on your behalf.
Each dwelling needs a compliant pathway to the network, and the configuration – shared trunk with individual branches, or individual lead-ins – depends on the site layout and NBN Co’s design requirements. A shared single conduit with no designed branching is the classic non-compliant shortcut. Get the configuration designed before trenching; it usually costs no more to build correctly.
Alongside the civil and stormwater design, before your construction certificate. That timing lets the conduits share trenches, keeps pits out of driveways and swept paths, gets the NBN application moving early, and means the compliance certification is a formality rather than an investigation.
Pit and Pipe (pitandpipe.com.au) designs and certifies telecommunications infrastructure for duplexes, villas and townhouse projects across NSW, working alongside the Contrive group’s civil, stormwater, traffic and architectural teams in Rouse Hill. See the group’s full services, or contact us to get your project connected – call +61 497 848 111 or email info@contriveconsultants.com.au.
What NSW councils look for in a DA waste management plan - demolition, construction, operational waste, bin storage, collection design…
Read articlePractical, budget-conscious design moves that lift a home to 7 stars under NatHERS - orientation, glazing, shading, insulation and sealing.
Read articleEvery hand-off between separate consultants costs time, money and accuracy. Why a coordinated multi-disciplinary team changes NSW project economics.
Read article